Doe Run Peru Begins Construction of Sulfuric Acid Plant for La Oroya Lead Circuit

 

La Oroya, Peru (PRWEB via PRWebDirect) July 25, 2007 -- Doe Run Peru has begun construction of a lead circuit sulfuric acid plant that will allow for the continued reduction of emissions of sulfur dioxide from the La Oroya smelter chimney, part of the company's continued commitment to improve air quality in La Oroya and meet its commitments with the Peruvian government and the local community.
PRWeb Press Release Newswire v7

The plant is the second of three related sulfuric acid projects (the first for the zinc circuit, has already been completed; the second for the lead circuit; and the third for the copper circuit), which comprise the last of nine projects undertaken under Doe Run Peru’s environmental operating agreement with the government (known by its Spanish initials, PAMA).

“This project carries an investment of more than $29 million. Its operation will involve the completion of a series of complementary projects we are carrying out concurrently,” said Juan Carlos Huyhua, president and general manager of Doe Run Peru. Those projects include completing updates to the effluents treatment plan, the electric substation that will power the acid plant, and in particular, the construction of a warehouse and dispatch terminal for the sulfuric acid that is produced as the sulfur dioxide is drawn out of the plant, Huyhua added.

Once the lead circuit’s acid plant is operational, Doe Run Peru expects to significantly reduce its emissions of sulfur dioxide.

Construction of the lead circuit plant is expected to be completed in September of 2008, according to a timetable approved by Peruvian government officials. Engineering work on the project began in October of 2006 and is being carried out by Fleck Chemical Industries of Canada and Graña y Montero of Peru. Equipment purchases for the facility began earlier this year.

Doe Run Peru’s total PAMA investment well surpasses the $107.5 million the company agreed to when it arrived to Peru in 1997. When all the projects are completed, which is on track for October of 2009, Doe Run Peru will have spent more than $244 million, approximately 2.3 times the original commitment.

About Doe Run Peru
Doe Run Peru is a mining and metals company operating in Peru's central Andes. The company has run the La Oroya metallurgical complex since 1997 and the Cobriza mine in Huancavelica since 1998, producing high quality refined metals while at the same time working to operate in a socially and environmentally responsible way.

For more information please visit: http://www.doerun.com.pe

Contact:
Victor Andres Belaunde
vbelaunde @ doerun.com.pe
Phone: +511-215-1285

###


 
 
 
 

 

 
CONTACT INFO

Victor Andres Belaunde
Doe Run Peru
Visit Our Site
+511-215-1285
E-mail us Here

ATTACHED FILES

No files were found for this release.

 
DISCLAIMER

If you have any questions regarding information in these press releases please contact the company listed in the press release. Please do not contact PRWeb. We will be unable to assist you with your inquiry. PRWeb disclaims any content contained in these releases. Our complete disclaimer appears here.

 



  About PRWeb Direct™   |   Search Engine Promotion of Your News  |  Get Free Publicity   |  How to Write a Press Release   |  Contact Information


© Copyright 1997-2005, PR Web™. All Rights Reserved